Fields 1 2
Year 2019-20 2018-19
Budget head Gok BBMP
Year of Handing over 2016 2016
Condition of lake during handing over partially develpoed undeveloped lake
Name of work
Improvements to Kalenaagrahara
Water reclamation plant at Kalena agrahara Lake
Sanctioned Amount (crores) 1.50 0.75
Job code 308-19-000050 308-18-000004
Work order date 19-02-2020 25-07-2018
Work order amount (crores w/o GST) 9.72 0.75
Components taken
Water body fencing, outlet, and pathway improvments
STP
Billed Amount (crores) 10.03 0.75
Date of completion 30-03-2022 01-07-2021
Remarks