Fields 1 2
Year 20152020
Budget head P-2175, Improvements to new lakesP-3664, Improvements and development of lakes in K R Puram consitituency assembly
Year of Handing over FEE 139 ECO 2008 dated 19.04.2010FEE 139 ECO 2008 dated 19.04.2010
Condition of lake during handing over
Name of work
Development to Devasandra Lake
Improvements to Devasandra Lake
Sanctioned Amount (crores) 0.85 2.00
Job code 308-15-000011308-20-000029
Work order date 20.03.201516.09.2020
Work order amount (crores w/o GST) 0.87 2.19
Components taken
Pathway, retaining wall
Chain Link Fencing, Walkway Improvement, Construion of Rest Room, Construion of Security Room, Outlet Improvements and Pipe line Works
Billed Amount (crores) 0.87 2.19
Date of completion 21.09.201520.05.2022
Remarks