Fields 1 2 3
Year 2022-232017-202017-18
Budget head Amrutha Nagorathana GrantsCM Nava Nagorathana GrantsImprovements to Lakes
Year of Handing over UDD/449/BAS/2016 DT:14.09.2016UDD/449/BAS/2016 DT:14.09.2016UDD/449/BAS/2016 DT:14.09.2016
Condition of lake during handing over Undeveloped LakeUndeveloped LakeUndeveloped Lake
Name of work
PACKAGE-7 1) Providing fencing and other improvements work in Sarakki lake 2) Development and Maintenance of Sarakki lake in ward No.187 3) Development and Maintenance of Hulimavu Lake Arkere in ward No.193 4) Development and Maintenance of Arkere Lake in ward No 193 5) Development and Maintenance of Agara Lake in ward No 174 6) Development and Maintenance of Singasandra A Block lake in ward No.191 7) Development and Maintenance of Singasandra B Block lake in ward No.191 8) Development and Maintenance of Somasundra playa lake in ward No.174
Improvements to walking path, Lighting & other works in Ibblur lake & Surroundings Improvements to Somsundrapalya Chikkabegur & Singasandra lake & Development of Agara lake
Development of Somsundarapalya Lake
Sanctioned Amount (crores) 12.00 15.00 4.00
Job code 308-23-000115308-21-000042308-18-000005
Work order date 15.03.202330.07.202119.03.2018
Work order amount (crores w/o GST) 10.23 12.74 4.27
Components taken
1.Park Area Development (Walkway improvements) 4. Providing Outer body fencing with RCC Retaining 5.Providing Gym & play equipment & Benches 6.Construction of Yoga Platform
1.Chain Link Fencing For Water body , 2.Chain Link Fencing For Outer Body 3.Walk Way Improvements 4.Toilet Block 5. Access Control 6. Security Room 7. Gazebo (1 Nos) 8 .Electrical Work (Street Lighting for walk way-Solar light) 9 .Water Supply Pipe Line 10.Immerrsion idol tand
1. Improvement to Lake bed 2.Strengthing of Main bund
Billed Amount (crores) 1.46 13.81 4.26
Date of completion completed30.05.202311.12.2019
Remarks