Fields 1
Year 2019-20
Budget head C M Nava Nagarothana
Year of Handing over FEE/172/ECO/2007 DT:28.03.2008
Condition of lake during handing over Undeveloped Lake
Name of work
Package -6 Development of Chokkabasthi Lake, Improvement to Puttenahalli Lake,Talghatapura lake, Improvement and development at Uttrahalli Lake in ward no 184, Construction of RCC retaining wall, RCC drains with covering slabs to Devarakere Lake and surrounding area in ward no 161, Balance development works of Byrasandra Lake in ward no 1533
Sanctioned Amount (crores) 15.00
Job code 308-20-000006
Work order date 24.03.2020
Work order amount (crores w/o GST) 13.84
Components taken
1.Improvement to lake bed 2.Improvement to Ring Bund 3.Walkway with catch drain construction 4.Chainlink fencing for Water body & Outer body
Billed Amount (crores) 15.17
Date of completion completed
Remarks