Fields | 1 | 2 |
---|---|---|
Year | 2022-23 | 2016-17 |
Budget head | P3803 15th finance | P3106 Nagarothana Works |
Year of Handing over | 2007 | 2007 |
Condition of lake during handing over | Undeveloped Lake | Undeveloped Lake |
Name of work | Developmental work to Nayandahalli Lake | Package-L6: 1) Improvements of Mallathahalli lake2) Improvements of Ullala lake3) Improvements to Nayandahalli Lake |
Sanctioned Amount (crores) | 7.50 | 3.00 |
Job code | 308-23-000001 | 308-17-000010 |
Work order date | 29-08-2022 | 08-03-2017 |
Work order amount (crores w/o GST) | 6.74 | 8.75 |
Components taken | Desilting of tank, RCC boundary wall with grill, pathway work,security room with toilet block,water body fence repair work, entrance gates 3 no. | Desilting, revetment, inlet, outlet, pathway |
Billed Amount (crores) | 6.18 | 8.67 |
Date of completion | 23-02-2024 | 02-08-2018 |
Remarks | Work completed | Work completed |