Fields 1 2 3
Year 2019-202022-232022-24
Budget head POWCM Amrutha Nagarothana UDD 299 MNY 2022 (E)
Year of Handing over UDD 449 2016 BAS dated:14.09.2016UDD 449 2016 BAS dated:14.09.2016
Condition of lake during handing over Undeveloped LakeUndeveloped Lake
Name of work
Reconstruction of breached bund and other related works at Doddabidrakallu Lake.
PACKAGE-19 2) Comperhensive Development of Doddabidarakallu Lake
PROVIDING CHAIN LINK FENCING TO Doddabidarakallu Lake
Sanctioned Amount (crores) 1.00 6.50 0.25
Job code 308-20-000022308-23-000124308-22-000099
Work order date 13-03-202024-03-202318-05-2022
Work order amount (crores w/o GST) 1.02 15.11 0.22
Components taken
Strengthening of Main Bund at Breached portion, benching & Pitching to Main bund
Sewage diversion drain, formation of ring bund, desilting, construction of inlet & silt trap, culverts, Revetment, Installation of gate
Boundary Fence
Billed Amount (crores) 0.53 5.40 0.22
Date of completion 30-10-2023
Remarks
Work completed final bill to be submitted
Work in Progress
work completed