Fields | 1 | 2 | 3 |
---|---|---|---|
Year | 2019-20 | 2022-23 | 2022-24 |
Budget head | POW | CM Amrutha Nagarothana UDD 299 MNY 2022 (E) | |
Year of Handing over | UDD 449 2016 BAS dated:14.09.2016 | UDD 449 2016 BAS dated:14.09.2016 | |
Condition of lake during handing over | Undeveloped Lake | Undeveloped Lake | |
Name of work | Reconstruction of breached bund and other related works at Doddabidrakallu Lake. | PACKAGE-19 2) Comperhensive Development of Doddabidarakallu Lake | PROVIDING CHAIN LINK FENCING TO Doddabidarakallu Lake |
Sanctioned Amount (crores) | 1.00 | 6.50 | 0.25 |
Job code | 308-20-000022 | 308-23-000124 | 308-22-000099 |
Work order date | 13-03-2020 | 24-03-2023 | 18-05-2022 |
Work order amount (crores w/o GST) | 1.02 | 15.11 | 0.22 |
Components taken | Strengthening of Main Bund at Breached portion, benching & Pitching to Main bund | Sewage diversion drain, formation of ring bund, desilting, construction of inlet & silt trap, culverts, Revetment, Installation of gate | Boundary Fence |
Billed Amount (crores) | 0.53 | 5.40 | 0.22 |
Date of completion | 30-10-2023 | ||
Remarks | Work completed final bill to be submitted | Work in Progress | work completed |