Fields 1 2 3 4 5
Year 01-11-20102015-162016-172021-222023-24
Budget head P2093 Dasarahalli kere lakeNagarothana grantsPOWPOW221802/P3028 Maintennace of Lakes current works
Year of Handing over FEE 139 ECO 2008, Bengaluru Dated:19/04/2010FEE 139 ECO 2008, Bengaluru Dated:19/04/2010FEE 139 ECO 2008, Bengaluru Dated:19/04/2010FEE 139 ECO 2008, Bengaluru Dated:19/04/2010FEE 139 ECO 2008, Bengaluru Dated:19/04/2010
Condition of lake during handing over undeveloped lakeundeveloped lake undeveloped lakeundeveloped lakeundeveloped lake
Name of work
Design Construction supply Instalation and commissioning of water reclaimation plant (WRP) of 1MLD capacity woth operation and maintainance for 5 Years at Dasarahalli Lake
Comprehensive Development of Dasarahalli Lake Phase-2
Development of Dasarahalli Lake.
Providing chain link fencing to Dasarahalli Lake
Pathway cleaning and wet land desiting at dasarahalli lake
Sanctioned Amount (crores) 4.05 3.00 0.75 0.15 0.48
Job code 308-11-000010039-12-000027308-17-000020308-22-000094304-24-000036
Work order date 427.6423/5/201316-11-201705-10-202212-01-2023
Work order amount (crores w/o GST) 0.00 2.93 0.71 0.13 0.33
Components taken
Construction supply Instalation and commissioning of water reclaimation plant (WRP) of 1MLD capacity woth operation and maintainance for 5 Years
Construction of retaining wall at Slum Side, Walkway crossing at Inlet-2, Walkway crossing at Inlet-1, Constructing drain at inlet-1, Providing Kerb stones for walkway, Providing Entrance gate 2 Nos, Constructing Security room, Construction of Immerse tank, Chainlink fencing Creation of wetland at inlet-1 & inlet-2.
Inlet retaining wall and footbridge, benches, Park area development
Fencing of Lakes (P-3868)
Pathway cleaning
Billed Amount (crores) 4.27 2.93 0.33 0.12 0.35
Date of completion 18-02-2016 26-06-202225-06-2024
Remarks
Work Completed
Work Completed
Work Completed
Work Completed
work completed