Fields 1
Year 2018-19
Budget head P2741
Year of Handing over UDD 445 BDA 2014, Bangalore. Dated: 06-02-2016
Condition of lake during handing over Undeveloped Lake
Name of work
Package-A: Improvements to Uttarahalli, Kodigesingasandra, Somasundarapalya, Sadarmangala, Garudacharpalya, Halasuru, Basapura, Doddakannenahalli, Ullala, Kalena Agrahara, Lakes.
Sanctioned Amount (crores) 1.00
Job code 308-19-000050
Work order date 19-02-2020
Work order amount (crores w/o GST) 9.72
Components taken
Gazebo, Drain, turfing, revetment
Billed Amount (crores) 9.71
Date of completion 30-03-2022
Remarks
Work completed