Fields 1
Year 2022-23
Budget head Amruth nagarothana
Year of Handing over UDD 445 BDA 2014, Bangalore. Dated: 06-02-2016
Condition of lake during handing over Undeveloped gate
Name of work
Package 13: 1.Providing water body fencing, waste weir repair works at Chinnappanahalli lake 2.Desilting, Pathway, Water body fencing, and other works in Sowl kere lake 3.Balance developmental works at Panathur lake 4.Comprehensive developmental works at Bhoganahalli lake 5.Comprehensive developmental works at Hoodi giddanakere lake 6.Balance developmental works at Varanasi lake 7.Balance developmental works at Gunjur palya lake.
Sanctioned Amount (crores) 4.00
Job code 308-23-000090
Work order date 12-12-2022
Work order amount (crores w/o GST) 9.92
Components taken
Desilting, revetment, main bund improvements, ring bund formation
Billed Amount (crores) 6.13
Date of completion
Remarks
work in progress