Fields | 1 | 2 |
---|---|---|
Year | 2022-23 | 2016-17 |
Budget head | Amruth nagarothana | 3106 |
Year of Handing over | UDD 445 BDA 2014, Bangalore. Dated: 06-02-2016 | UDD 445 BDA 2014, Bangalore. Dated: 06-02-2016 |
Condition of lake during handing over | Undeveloped Lake | |
Name of work | Package 13: 1.Providing water body fencing, waste weir repair works at Chinnappanahalli lake 2.Desilting, Pathway, Water body fencing, and other works in Sowl kere lake 3.Balance developmental works at Panathur lake 4.Comprehensive developmental works at Bhoganahalli lake 5.Comprehensive developmental works at Hoodi giddanakere lake 6.Balance developmental works at Varanasi lake 7.Balance developmental works at Gunjur palya lake.
| Package-L 2: 1) Development of Devarabeesanahalli Lake Phase-12)Development of Siddapura Lake Phase-13) Development of Panathur lake Phase-1.
|
Sanctioned Amount (crores) | 1.00 | 2.50 |
Job code | 308-23-000090 | 308-17-000006 |
Work order date | 12-12-2022 | 01-07-2017 |
Work order amount (crores w/o GST) | 9.92 | 8.46 |
Components taken | Outer Body fencing (Partially), water body fencing, Gravel laying, kerb
| Desilting, Main Bund Formation, Rind Bund Formation, Wetlands - 2No's, Islands-2No's, Revetment, turfing, Inlets-1No Pipe culvert-2Nos,, Diversion drain, Fencing(Partially), Waste Weir with kalyani
|
Billed Amount (crores) | 6.13 | 8.45 |
Date of completion | 20-4-2019 | |
Remarks | work in progress
| Work completed
|