Fields | 1 | 2 |
---|---|---|
Year | 2021-22 | 2019-20 |
Budget head | P3868 | P3743-Mukhya Mantrigala Nava Nagarothana Grants |
Year of Handing over | UDD 449 BDA2016, Bangalore Dated: 04-09-2016 | UDD 449 BDA 2016, Bangalore, Dated: 14-09-2016 |
Condition of lake during handing over | ||
Name of work | Providing chain link fencing to Nalurahalli lake | Packages-VIII : Development of Nalluralli tank, Improvements to Sowl Kere, Sigehalli lake and Construction of STP, Construction of STP at Chinnappanahalli Lake in Ward No.85, Construction of STP at Munnekolalu Lake in Ward No.85 |
Sanctioned Amount (crores) | 0.75 | 4.00 |
Job code | 308-22-000043 | 308-20-000010 |
Work order date | 27-03-2023 | 24-03-2020 |
Work order amount (crores w/o GST) | 0.65 | 14.75 |
Components taken | Fencing (Partially) Waste Weir, Sluice , wing walls | Diversion channel, Fencing (Partially), Inlet, Gate |
Billed Amount (crores) | 0.64 | 14.03 |
Date of completion | 25-09-2023 | 31.12.2024 |
Remarks | Work completed | Work completed |