Fields | 1 | 2 |
---|---|---|
Year | 2018-19 | 2016-17 |
Budget head | P2741 | NAGAROTHANA GRANTS |
Year of Handing over | UDD 445 BDA 2014, Bangalore. Dated: 06-02-2016 | UDD 445 BDA 2014, Bangalore. Dated: 06-02-2016 |
Condition of lake during handing over | Undeveloped Lake | Undeveloped Lake |
Name of work | Package-A: Improvements to Uttarahalli, Kodigesingasandra, Somasundarapalya, Sadarmangala, Garudacharpalya, Halasuru, Basapura, Doddakannenahalli, Ullala, Kalena Agrahara, Lakes.
| Package-L 4: 1)Development of Sadaramangala Lake Phase-1, 2) Development of Bhattarahalli Lake Phase-13) Development of GarudacharPalya Lake, Phase-1, 4) Providing Chain Link Fencing to Hoodi Giddanakere |
Sanctioned Amount (crores) | 0.75 | 1.50 |
Job code | 308-19-000050 | 308-17-000008 |
Work order date | 19-02-2020 | 07-01-2017 |
Work order amount (crores w/o GST) | 9.72 | 9.05 |
Components taken | Gazebo, Diversion Drain (Partial), Gates-2Nos, pathway cobble, kerb, outer fencing
| Desilting,Main bund formation, Ring bund formation, Wetland Formation, Waste weir culvert, Inlet, Diversion channel, Water body fencing |
Billed Amount (crores) | 9.71 | 9.04 |
Date of completion | 30-3-2022 | 20-05-2022 |
Remarks | Work Completed
| Work Completed |