Fields 1
Year 2022-23
Budget head Amruth nagarothana
Year of Handing over UDD 39 BDA 2019, Bangalore. Dated 11-12-2019
Condition of lake during handing over Sewage entrying from all the inlets no diversion chanels and levels of the inlets not properly provided flooding happining for the surrounding areas, Lake was siltted up. Lake has encroachment
Name of work
Package 14: 1)Developmental works in Doddanekundi lake 2) Development of Doddanekkundi lake in ward no 85 Doddanekkundi
Sanctioned Amount (crores) 15.00
Job code 308-23-000088
Work order date 09-12-2022
Work order amount (crores w/o GST) 13.09
Components taken
Inlets with Silt traps -4No's,Waste weir with sluice-1 No, Desilting, Diversion Pipeline, Improvements to existing Bund, Road side Catch Drain With Fencing, Pathway formation, kerb resetting, Water body fencing, security room construction with toilet-2 Nos, Foot Bridge-2 Nos, Existing Drain Improvements, Fencng for outerbody after removing encroachment.
Billed Amount (crores) 11.74
Date of completion
Remarks
work in progress