Fields | 1 |
---|---|
Year | 2022-23 |
Budget head | Amruth nagarothana |
Year of Handing over | UDD 39 BDA 2019, Bangalore. Dated 11-12-2019 |
Condition of lake during handing over | Sewage entrying from all the inlets no diversion chanels and levels of the inlets not properly provided flooding happining for the surrounding areas, Lake was siltted up. Lake has encroachment |
Name of work | Package 14: 1)Developmental works in Doddanekundi lake 2) Development of Doddanekkundi lake in ward no 85 Doddanekkundi
|
Sanctioned Amount (crores) | 15.00 |
Job code | 308-23-000088 |
Work order date | 09-12-2022 |
Work order amount (crores w/o GST) | 13.09 |
Components taken | Inlets with Silt traps -4No's,Waste weir with sluice-1 No, Desilting, Diversion Pipeline, Improvements to existing Bund, Road side Catch Drain With Fencing, Pathway formation, kerb resetting, Water body fencing, security room construction with toilet-2 Nos, Foot Bridge-2 Nos, Existing Drain Improvements, Fencng for outerbody after removing encroachment.
|
Billed Amount (crores) | 11.74 |
Date of completion | |
Remarks | work in progress
|