Fields 1 2
Year 2022-23 2019-20
Budget head Amruth nagarothana Mukhya Mantrigala Nava Nagarothana Grants
Year of Handing over UDD 449 BDA 2016, Bangalore, Dated: 14-09-2016 UDD 449 BDA 2016, Bangalore, Dated: 14-09-2016
Condition of lake during handing over Undeveloped lake
Name of work
Package 13: 1.Providing water body fencing, waste weir repair works at Chinnappanahalli lake 2.Desilting, Pathway, Water body fencing, and other works in Sowl kere lake 3.Balance developmental works at Panathur lake 4.Comprehensive developmental works at Bhoganahalli lake 5.Comprehensive developmental works at Hoodi giddanakere lake 6.Balance developmental works at Varanasi lake 7.Balance developmental works at Gunjur palya lake.
Development of Jimkenahalli Lake, Gunjur Palya Lake, Improvements to Begur lake and Siddapura lake Packages- I Annexure-1Sl No 28 15 11 27
Sanctioned Amount (crores) 2.00 3.00
Job code 308-23-000090 308-20-000003
Work order date 12-12-2022 26-03-2020
Work order amount (crores w/o GST) 9.92 19.41
Components taken
Inlets Construction -2No's, Diversion Pipeline, Entrance Gate-1 No, Wetland bund formation, Gravel laying, kerb
Desilting, Bumd formation, Ring Bund formation, wetland, Revetment, Outer body Fencing (Partial missing bits), pipe culverts, turfing
Billed Amount (crores) 6.13 17.21
Date of completion 29-07-2022
Remarks
work in progress
work completed