Fields 1
Year 2022-23
Budget head Amruth nagarothana
Year of Handing over UDD 449 BDA 2016, Bangalore, Dated: 14-09-2016
Condition of lake during handing over Undeveloped lake
Name of work
Package-15: Comprehensive developmental works at Junnasandra lake , Comprehensive developmental works at Gunjuru Karmelaram lake, Comprehensive developmental works at Gunjuru Mavinakere lake, Providing fencing to Pattandur Agrahara lake-1 Providing fencing to Pattandur Agrahara lake-2 Development of Gunnjur Mavinakere lake in ward no 149 varthur
Sanctioned Amount (crores) 8.00
Job code 308-23-000113
Work order date 15-03-2023
Work order amount (crores w/o GST) 14.40
Components taken
Desilting, Main Bund Strengthening, Rind Bund Formation, Revetment,Island formation, inlets-3 Nos, Wetlands-2 No's, Waste weir Improvements, Pipe culverts-5 Nos, Fencing (Partially)
Billed Amount (crores) 4.35
Date of completion
Remarks
work in progress