Fields | 1 |
---|---|
Year | 2022-23 |
Budget head | Amruth nagarothana |
Year of Handing over | UDD 449 BDA 2016, Bangalore, Dated: 14-09-2016 |
Condition of lake during handing over | Undeveloped lake |
Name of work | Package-15: Comprehensive developmental works at Junnasandra lake , Comprehensive developmental works at Gunjuru Karmelaram lake, Comprehensive developmental works at Gunjuru Mavinakere lake, Providing fencing to Pattandur Agrahara lake-1 Providing fencing to Pattandur Agrahara lake-2 Development of Gunnjur Mavinakere lake in ward no 149 varthur
|
Sanctioned Amount (crores) | 8.00 |
Job code | 308-23-000113 |
Work order date | 15-03-2023 |
Work order amount (crores w/o GST) | 14.40 |
Components taken | Desilting, Main Bund Strengthening, Rind Bund Formation, Revetment,Island formation, inlets-3 Nos, Wetlands-2 No's, Waste weir Improvements, Pipe culverts-5 Nos, Fencing (Partially)
|
Billed Amount (crores) | 4.35 |
Date of completion | |
Remarks | work in progress
|