Fields | 1 | 2 | 3 |
---|---|---|---|
Year | 2024-25 | 2021-22 | 2019-20 |
Budget head | P0290 (Fencing of BBMP Vacant land | P3868 (fencing of lakes) | Shubra Benagluru Grants |
Year of Handing over | UDD 449 BDA 2016, Bangalore, Dated: 14-09-2016 | UDD 449 BDA 2016, Bangalore, Dated: 14-09-2016 | UDD 449 BDA 2016, Bangalore, Dated: 14-09-2016 |
Condition of lake during handing over | Undeveloped Lake | ||
Name of work | Providing Chain link fencing to Rampura Lake
| Providing Chain link fencing to Balance reach at Rampura Lake | Development of Rampura lake Phase-1 |
Sanctioned Amount (crores) | 1.60 | 0.99 | 40.00 |
Job code | 308-25-000177 | 308-22-000087 | 308-20-000107 |
Work order date | 12-02-2025 | 16-09-2022 | 09-02-2021 |
Work order amount (crores w/o GST) | 1.20 | 0.84 | 35.04 |
Components taken | Balance Outer Body Fencing in progress (1486m)
| Fencing 1486 m | Desilting, inlets with silt traps-3 no's, waste weir-2 No's , Main Bund improvements, Ring Bund formation, Revetment, diversion drains -2 no's , Foot bridge -2 No's, Sluice-2No's, security room cum Toilet Block-1 No, Wetlands-2 No's, Island formation -2No, Fencing - 547.70M, turfing, Deck Slab over 4m drain-2No, Deck slab over 2.5m darin-1 No. |
Billed Amount (crores) | 0.00 | 0.78 | 32.45 |
Date of completion | 15-03-2024 | ||
Remarks | Work in progress
| Completed | Work in progress |