Fields | 1 | 2 |
---|---|---|
Year | 2022-23 | 2022-23 |
Budget head | AMRUTHA NAGAROTHANA 2022-23 | |
Year of Handing over | ||
Condition of lake during handing over | ||
Name of work | PACKAGE-9 1)EMERGENCY WORKS AT HANDRAHALLI LAKE, 2) STRENGTHENING OF WETLAND BUND, SILTRAP CONSTRUCTION & OTHER WORKS AT ULLALA LAKE, 3) PROVIDING CHAIN LINK FENCING, PATHWAY IMPROVEMENTS & OTHER WORKS IN DUBASIPALYA LAKE, 4) DEVELOPMENTAL WORKS AT GANDHINAGARA HOSAKERE LAKE, 5) DEVELOPMENTAL WORKS AT LINGADERANAHALLI-13 LAKE.
| Demolition & Providing chain link fencing to Encroachment removed Portion of lakes boundary in Rajarajeshwari Nagar Zone
|
Sanctioned Amount (crores) | 2.00 | 0.90 |
Job code | 308-23-000120 | 308-22-000011 |
Work order date | 20.03.2023 | 09.09.2022 |
Work order amount (crores w/o GST) | 13.35 | 0.79 |
Components taken | PROVIDING SEWAGE DIVERSION PIPE LINE, CONSTRUCTION OF HUME PIPE CULVERT AT WEST SIDE OF THE LAKE (SURFACE WATER)
| Chainlink Fencing
|
Billed Amount (crores) | 2.11 | 0.78 |
Date of completion | 09-01-2025 (Final bill to be submitted) | 08.02.2024 |
Remarks |